A display does not fail because the lights were bad. It fails because someone added up the watts on the box, picked a transformer that matched that number, and switched everything on at once. Two weeks later half the strings are dim, one driver is hot enough to smell, and the breaker that "randomly" trips is the one nobody calculated.
This guide is the calculation an installer actually runs before quoting a job: real wattage, power factor, derating, transformer VA, voltage drop and circuit allocation. Every table below can be copied straight into a submittal or an RFQ.
1. Start with real wattage, not the number on the box
Every lighting product has three different wattage figures, and they are not interchangeable:
- Nominal / rated wattage — what the datasheet prints. Usually measured at a fixed test voltage, often 25 °C, often "typical" rather than worst case.
- Actual draw at your supply voltage — a 230 V product run at 240 V draws roughly 4% more current, and therefore about 8% more power for a resistive-ish load.
- Inrush — the spike in the first 10–200 ms after switch-on, when driver capacitors charge. It is not part of the running load, but it decides whether your breaker holds.
For planning, use the worst case running draw you can find, then apply derating. The figures below are the ones we publish for our own product families, and they are a reasonable industry reference:
| Load type | Typical draw | Notes |
|---|---|---|
| Single-colour 5 mm LED in a string | 0.06 W per LED | Two-wire series string, no controller |
| Single-colour string, per metre | 3 – 6 W / m | Depends on LED pitch (10 cm vs 20 cm) |
| Round rope light, 230 V | 5 – 14 W / m | Higher figure = denser LED pitch |
| RGB pixel point (WS2811-class, 12 V) | 0.3 W at full white | 0.1 W when running a single colour |
| Motif / sculpture, per m² of lit face | 25 – 60 W / m² | Depends on fill density and LED size |
| Floodlight washing a façade | 30 – 200 W per fixture | Read the driver label, not the LED chip |
If a supplier quotes a sculpture by "number of LEDs" only, ask for the total wattage per square metre of face. That single number is what you size everything else from.
2. The total load formula (and the power factor most people forget)
Watts are what you pay for. Volt-amperes (VA) are what the transformer and the breaker have to carry. They are only the same number when the power factor is 1.0 — which LED drivers, with their switched-mode supplies, almost never are.
VA = W ÷ power factor
Single-colour LED strings without a driver: PF ≈ 0.9
LED drivers and adapters, good quality: PF 0.7 – 0.95
Cheap unbranded adapters: PF 0.5 – 0.6
So a 1,000 W display running on mediocre adapters at PF 0.55 needs 1,818 VA of transformer capacity, not 1,000. This is the single most common sizing error we see in submittals, and it is why a "1 kVA transformer" from a marketplace listing browns out under a real load.
3. Worked example: a 20 m tree plus 200 m of street pole decorations
Take a realistic municipal job:
- 20 m commercial tree, 1,800 RGB pixels at full white: 1,800 × 0.3 W = 540 W
- Tree topper star, 60 W, plus 400 W of single-colour garland: 460 W
- 40 street-pole motifs, 15 W each: 600 W
- Cross-street catenary strings, 300 m at 5 W/m: 1,500 W
- Controller and network gear: 80 W
Total running load = 3,180 W.
Now derate. Continuous loads should not exceed 80% of the supply rating — a rule that exists because breakers and transformers are rated for a thermal steady state, and a Christmas display runs for six weeks, not six minutes.
Required supply = 3,180 W ÷ 0.80 = 3,975 W
In VA at PF 0.85 = 4,676 VA → specify 5 kVA of transformer capacity, split across at least three distribution points.
That is not a number you can put on one outdoor socket. It is three or four transformer stations, each within cable reach of its own group of motifs. Which brings us to the part that actually causes dim lights.
4. Transformer sizing: 12 V, 24 V, and why "bigger" is not better
Low-voltage displays run on 12 V or 24 V because it is safer in public spaces and cheaper to cable. The trade-off is current: a 300 W load draws 25 A at 12 V and only 12.5 A at 24 V. Double the voltage, half the current, one quarter the losses for the same cable.
Three rules that hold for almost every project:
- Size the transformer to the group it feeds, not to the whole display. Many small units near their loads beat one big unit 60 m away.
- Leave 20–25% headroom. Transformers run cooler, last longer, and have room for the extra string the client always asks for in week two.
- Check that it can be dimmed. If the show needs dimming or animation, the supply has to be dimmer-compatible; a standard transformer will buzz, flicker or die early.
| Group load (W) | 12 V current | 24 V current | Suggested supply (VA, with 25% headroom) |
|---|---|---|---|
| 100 W | 8.3 A | 4.2 A | 150 VA |
| 200 W | 16.7 A | 8.3 A | 300 VA |
| 300 W | 25.0 A | 12.5 A | 400 VA |
| 500 W | 41.7 A | 20.8 A | 700 VA |
| 1,000 W | 83.3 A | 41.7 A | 1,500 VA — or split it |
Above roughly 500 W per group, split the load rather than buying a bigger box. Long 12 V runs at high current is where "the last ten metres of my string are yellow" comes from.
5. Voltage drop: the table nobody puts in the catalogue
Copper has resistance. Over a long run, some of your 12 V never reaches the far end, and the LEDs there go dim and warm-shifted. The practical limit for decorative low-voltage work is 10% drop at the furthest fixture — 1.2 V on a 12 V system.
Maximum one-way cable run (metres) before you hit 10% drop, 12 V DC, copper, 10% tolerance:
| Cable cross-section | 50 W group | 100 W group | 200 W group |
|---|---|---|---|
| 1.5 mm² | 12 m | 6 m | 3 m |
| 2.5 mm² | 21 m | 10 m | 5 m |
| 4.0 mm² | 33 m | 16 m | 8 m |
On a 24 V system, multiply those distances by four. This one line is the strongest argument for specifying 24 V on any large site: the same cable, four times the reach, or the same reach with far less copper.
If the run has to be longer, you have three options — increase cable size, move the transformer closer to the load, or go to a 24 V system. Do not "solve" it by buying a higher-wattage transformer; the drop is set by cable and current, not by supply size.
6. Circuit allocation and controller channels
Once the totals are known, split them into circuits. A few habits that prevent most on-site faults:
- One circuit per zone, one zone per breaker. A fault in one motif must not darken a whole street.
- Keep lighting circuits separate from motor loads — rotating reindeer, snow machines, anything with a motor injects noise back onto the line.
- Group by control, not by geography. If a facade animates as one effect, it wants one controller channel, even if the pieces are 40 m apart.
- Count channels before you buy controllers. 1,800 pixels on a 12 V WS2811 run means roughly 55 A at full white — that is a power-injection problem, not a controller problem. Inject power every 5–8 m or every 150–200 pixels.
- Stagger switch-on. A controller that powers zones 200 ms apart removes most inrush trips without any extra hardware.
7. Protection, enclosures and compliance
The electrical side of a public display is not a place to improvise:
- RCD / GFCI protection on every outdoor circuit, 30 mA. Non-negotiable for anything the public can touch.
- IP-rated junctions. IP65 minimum for outdoor connectors, IP67 for anything that sits in standing water or gets jet-washed. IP44 is an indoor number.
- Earthing on all metal frames, and a single bonded earth point per structure.
- Components listed to the destination market. CE and RoHS for the EU and UK, UL/ETL-listed components for North America. "CE-style" stickers on unbranded drivers are common and are not the same thing.
- Thermal check. Enclosures need airflow; a sealed box in a Dubai summer will cook a driver rated for 40 °C ambient.
8. The one-page worksheet
Copy this into your submittal and fill it in. If every row is answered, the display will run:
| # | Item | Formula / value |
|---|---|---|
| 1 | Total running load | Sum of all fixtures at worst-case draw (W) |
| 2 | Power factor | From driver datasheet, typically 0.7 – 0.95 |
| 3 | Apparent load | Step 1 ÷ Step 2 (VA) |
| 4 | Required supply | Step 3 ÷ 0.80 (VA) |
| 5 | Number of groups | Step 1 ÷ chosen transformer size; keep ≤ 500 W per group |
| 6 | System voltage | 12 V (short runs) or 24 V (long runs / large sites) |
| 7 | Cable size and run length | Check against the voltage-drop table in section 5 |
| 8 | Breakers | Circuit current ≤ 80% of breaker rating |
| 9 | Inrush control | Staggered switch-on, or C-curve breakers |
| 10 | Protection | 30 mA RCD/GFCI, IP65+ junctions, bonded earth |
| 11 | Controller channels | Zones × effects; power injection points counted |
| 12 | Compliance | CE + RoHS, or UL/ETL-listed components |
9. The three mistakes that account for most failures
Mistake 1 — sizing to watts and forgetting VA. A 1,000 W display on PF 0.55 adapters pulls 1,818 VA. The transformer derates, the voltage sags, the animation glitches, and everyone blames the controller.
Mistake 2 — one big transformer, long 12 V runs. The far end goes yellow and dim because the cable, not the supply, is the limit. The fix is distribution, not a bigger box.
Mistake 3 — no headroom and no stagger. Running a supply at 100% of rating for six weeks is a slow failure; switching everything on in the same instant is a fast one. Twenty percent headroom and 200 ms of staggering cost almost nothing.
What to put in the RFQ
You do not need to solve the whole electrical design before contacting a supplier — but you do need to send the right inputs. Ask for: total wattage per element, recommended supply size and quantity, system voltage, maximum run length per group, IP rating of every connector, and the compliance listing for the drivers. A supplier who cannot answer those four lines in writing is quoting a decoration, not a display.